 |
|
Concrete cracks that are
wider than .035” loose their aggregate interlock and are potential problems
waiting to happen.
|
|
One of the most perplexing segments of the
commercial flooring installation is how to handle joints in a concrete
slab. Flooring manufacturers insist that
flooring contractors “honor” all joints that are active (moving) and to cover
all dormant (non-moving) joints. The
general contractor, architects, designers or owners do not want to place a
joint cover down the middle of the room just to accommodate the flooring manufacture,
nor do they want to deal with the aesthetics left by the joint cover. With fast-track construction and a lack of
environmental controls, concrete joints are going to keep moving long after the
structure is occupied. Just how do you
know whether a concrete joint is active or dormant? You cannot look at a concrete joint and make
that determination. Just how long will
the concrete movement be a problem? We
know that 80 percent of the concrete movement peaks once the slab is stabilizes
normally in 6 – 9 months, but has been known to move for as long as 3 years
after the temperature and humidity has been stabilized. In this article we are going to look at this
dilemma and what needs to be done with joints.
Cracks in concrete cannot be prevented entirely, but they can be
controlled and minimized by properly designed joints.
Why concrete cracks
 |
|
When the control joints are too far apart or there are no
joints at all the concrete will develop its own joints. These cracks usually will quarter the slab
between other joints.
|
|
Concrete
is weak in tension and, therefore, if it’s natural tendency to shrink is
restrained, tensile stresses that exceed its tensile strength can develop,
resulting in cracking.
At early
ages, before the concrete dries out, most cracking is caused by temperature
changes or by the slight contraction that takes place as concrete sets and
hardens. Later, as the concrete dries,
it will shrink further and either an additional crack will form or existing
cracks will become wider.
Joints
provide relief from the tensile stresses, are easy to maintain and are less
objectionable than uncontrolled or irregular cracks.
Types of Concrete Joints
 |
|
A concrete slab being readied for preparation at many of the
control joints
|
|
Isolation
or Expansion Joints should be used wherever complete freedom of vertical and
horizontal movement is required between the floor and adjoining building
elements. Isolation joints should be used
at junctions with walls, (not requiring lateral restraints from the slab),
columns, drains, manholes and stairways.
Isolation joints are formed by the insertion of preformed joint filler
between the floor and the adjacent element.
The joint material should extend the full depth of the slab and not protrude
above it. Isolation joint are usually
active joints and are rarely without movement as they permit independent
vertical and horizontal movement between adjoining parts of the structure.
Construction joints are placed in a slab to define the extent of
individual placements, generally in conformity with a predetermined joint
layout. They are typically place at the
end of a day’s work but may be required when concrete placement is stopped for
longer than the setting time of concrete.
Construction joints may be doweled, keyed or butted depending upon the
intended usage of the slab. Regardless
of the usage construction joints are generally active and should be treated as
such.
Contraction or Control (Sawcuts) control joints are used to limit random,
out of floor joint, floor slab cracking.
These joints are usually on column lines, with intermediate joints
located at equal spaces between column lines.
These joints must be carefully designed and properly constructed if
uncontrolled cracking of concrete slabs are to be avoided. Depending upon the size of the large
aggregate, the maximum spacing of contraction joints should be 24 to 36 times
the thickness of the slab. For example,
in a 4-inch [100mm] thick slab the joint spacing should be about 10 feet [3
m]. It is further recommended that
joint spacing be limited to a maximum of 15 feet [4.5 m]. The depth of the sawcut should be a minimum
of 1/4 the depth of the thickness of the slab and/or a minimum of 1 inch
[25mm]. All construction joints should
be square or nearly so and L-shaped panels should be avoided. Sawcut joints are generally cut 4 – 12 hours
after the concrete has been finished.
Contraction/control joints can be either active or dormant. Active contraction joints are caused by the
slab not being dry or stabilized by temperature and humidity.
 |
|
Be sure to thoroughly clean out and vacuum the entire depth
of a saw cut. Getting the floor patch
the entire depth of the saw cut is imperative.
|
|
Concrete
movement is caused by temperature and moisture and/or humidity. The movement from thermal coefficient is
about twice that of moisture. This combined movement is a very small amount
roughly 1/8-inch per 100 l/f per 5 degrees Fahrenheit. It is enough to affect
the joints. For instance, say the joints
are 10 feet apart this would represent about 1/64-inch of movement at each
joint. Now imagine you have filled the
joint with high compressive strength Portland-based patching compound
restricting the slab movement. The
movement is going to occur, so something has to give. Is it going to be additional cracking, more
telegraphing of existing cracks or a pushing up of the patching compound?
The
moisture side of movement is even more complex.
Moisture in concrete causes expansion of the Portland cement, the only
part of concrete that moves. If a slab
is not entirely dry, water as a liquid will go to the bottom of the slab,
causing it to expand at the bottom. The
surface of the slab is exposed open elements which, normally is a drying
condition, as the slab dries the surface of the slab shrinks. This effect is known as slab curl. Slab curl is variable and will change as the
slab continues to dry. Once the slab is
dry the slab will go into equilibrium, this means the moisture content is equal
from top to bottom. That is when the
slab movement becomes dormant.
Flooring
contractors will send their installation crew out and start the floor
preparation with no idea of wither there is any potential for movement at the
concrete joints. First of all, a
calcium chloride test, done to ASTM F-1869 standards, will give you no indication
of the amount of moisture down in the slab they measure moisture movement at
the surface of the slab down as far as about 3/4”. The hygrometer probe test, (in-situ), done
to ASTM F-2170 standards, will give you a more realistic look at the internal
moisture content. If you were to do both
tests and the calcium chloride was indicating a slab dry enough to install over
and the hygrometer probe test was high you could expect the slab to be curled
and the joints to be active. Any high
compressive Portland-based filler, used to fill any active joints, will be
pushed up showing through the finished floor, only to be found on the
deficiency (punch) list.