 |
| Photo 2 |
|
For years flooring installers have
blamed concrete substrate headaches on the concrete contractors. So what is the
concrete side of the industry doing to address the needs of the flooring
installer? Well, there are actually cement/concrete associations that do
understand the frustrations of the flooring contractor and have printed
materials addressing the needs of both the concrete contractor and the flooring
contractor. The American Society of Concrete Contractors (www.ascconline.org)
and the American Concrete Institute (www.concrete.org) are two associations
that have literature available.
Following
are some of the concrete resources available: 302.2R-06: Guide for Concrete
Slabs that Receive Moisture-Sensitive Flooring Materials; 302.1R-04: Guide for
Concrete Floor and Slab Construction; ACI
117-06 Specifications for Tolerances for Concrete Construction and Materials
and Commentary; “Concrete Floors and Moisture” by Howard M. Kanare.
 |
| Photo 3 |
|
Many of
the flatness problems we deal with are due to the fact that in project
specification manuals, division three and division nine specifications are not
compatible. On the concrete side of the industry, concrete contractors are
required to follow ASTM E1155-96, “Standard
Test Method for Determining FF Floor Flatness and FL Floor Levelness Numbers.
The F-Number System is the American Concrete Institute (ACI
117) and Canadian Standards Association (CSA
A23.1) standard for the specification and measurement of concrete floor
flatness and levelness. F-Numbers replace the familiar “1/8th inch in ten
feet.”
The test
method utilizes a “dip stick” or F meter that is run across the slab to
accurately determine the flatness and levelness of the surface. Measurements
are then transferred electronically to a data sheet to give a blueprint of the
surface deviations.
There is no F-Number
equivalent to any straightedge spec. But, rough equivalents, in terms of
horizontal readings, can be given: an FF 25 is roughly equivalent to a single ±
¼-inch defect in 10 feet; an FF 50 is roughly equivalent to a single ± 1/8-inch
defect in 10 feet.
 |
| Photo 4 |
|
There are
some manufacturers/associations taking a position that there should be an FF
number measurement two weeks prior to an installation with readings across all
construction joints and a tolerance of 1/8” in ten foot radius. The ten foot
“radius” is also an issue as tests are conducted with the meters in one
direction only, they do not run perpendicular tests. This is where there is a
disconnection. The ASTM E1155 states that
testing needs to be done within 72 hours after placement of concrete and no
measurement lines within two feet of any slab boundary, construction joint,
isolation joint, blockout, penetration, or other discontinuity. On the flooring
side of the industry we are to test flatness of slabs using a ten foot straight
edge at any given point. My question here is how many installers out there are
checking slab flatness with a ten-foot straightedge?? That’s what I thought. I
know that there are a few installers that use a ten-foot straight edge but that
is only a small number compared to the six foot straight edges that are used on
a daily basis (Photos 1 and 2). So if the majority of installers are using a
six-foot straight edge, where did we get the requirement of a ten-foot straight
edge? The requirements are taken from the highway department. A ten-foot or
longer highway straight edge, also known as a paver’s straightedge is used to
cut or plane the surface of the concrete while it is still in what the concrete
industry refers to as plastic, hard enough that it holds its shape but still
soft enough to cut or plane. Most finish contractors will screed and then bull
float but not do a final straight edge cut as they feel it takes too much time;
they already have a difficult time with vapor barriers placed directly beneath
the slab in regards to edge curling, which is a whole other article. Photo 3
shows a 4-foot bull float and a 12-foot straight edge. This next statement was
taken from a highway specification
 |
| Photo 5 |
|
Straight
Edge: Immediately following the floating, and while the concrete is still
plastic, the contractor shall test the pavement surface for trueness by means
of a ten foot straight edge. All variations greater than one-fourth inch in ten
feet of length shall be eliminated by filling depressions with fresh concrete
and striking off projections and then re-floating.
So now
you know where the flooring industry got its tolerances for concrete flatness.
Wouldn’t
it be great if division 3 and division 9 of the project specification manual
stated; “Cement/concrete, and flooring contractors; please refer to divisions
3- concrete, and 9- finishes, to determine if mix designs and finish
specifications coincide with flooring manufacturers concrete substrate
requirements. If there are concerns, please address to architect or responsible
parties prior to bidding.”
What
would this require? That the architect, engineering, design, and specification
writing communities to work together and print this into their job
specifications.
 |
| Photo 6 |
|
Not all
the blame goes to the concrete contractor in regards to slab conditions; the
general contractor and other trades have a place in the chain of responsibility
with other factors also. Photos 4 and 5 show a basement slab that has had
moisture intrusion and a wood sub-floor with nothing being done to remove or
avoid as much of the moisture as possible. The two photos resemble common
occurrences in regards to new construction building. This is exactly why
installers/retailers need to conduct proper moisture testing procedures or make
certain that moisture testing was conducted. Ignorance does not mean innocence;
if the installer/retailer does not conduct moisture tests or make certain that
a moisture test was conducted they may be held responsible for more than just
the labor in most cases.
The Floor Covering
Industry White Paper Position Statement on Moisture Emission Testing/ Moisture
Emission Testing Responsibility and Qualifications forTesting, is a document
that addresses the need for third party independent testing, available for free
download at: http://www.cfiinstallers.com/Installers/MoistureWhitePaper1.pdf.
Another
area of concern for installers is lightweight concrete and gypsum-based
substrates. These types of products are used for less dead load weight
(constant weight on a structure) and sound suppression.
There are
no ASTM test methods to determine accurate
moisture vapor emissions rates in either of these. About the only tests that
can be conducted are the ASTM D-4263 “Mat”
test, and some electronic meters that read a gypsum base, keep in mind these
are only used as indicators. Between gypsum and lightweight pours, gypsum based
substrates (2,000 p.s.i.) have much lower compressive strengths than standard
concrete (3,000 p.s.i.), which explains why you can take the end of a
screwdriver and gouge the surface of the substrate. This type of substrate
makes it extremely difficult for installers, as most manufacturers will not
warranty a direct-glue over a gypsum based substrate and many times, installers
do not know what substrate they will be installing over until the day of
installation. There are installations that are being installed on a day to day
basis as glue-direct directly over gypsum based substrates even though they
will not be warranted, so what happens? It’s a roll of the dice. Some installers
will apply a latex/acrylic primer for bond strength, sometimes this works,
sometimes it doesn’t. The bond between the adhesive and the primer usually
won’t fail; it’s between the primer and the gypsum that will fail. Installers
who understand this try to persuade the end user or retailer to install
floating floor systems or other flooring that does not require adhesive for
bonding. If that’s not enough of a headache with gypsum, you also have the
movement issues. Gypsum poured over a plywood substrate can also have
deflection issues which causes the gypsum to fracture. Photo 6 shows a subfloor
that required support at the plywood joints then a self leveling gypsum product
was used to fill the rest of the area, this was done after three flooring
failures. There are manufacturers that have membrane systems and gypsum based
self leveling products with a higher p.s.i. that are placed over an existing
gypsum sub-floor, make sure to check with both the flooring manufacturer and
the product manufacturer for acceptance of these types of installations. Also,
when using a patching compound over a gypsum sub-floor use the white gypsum
based patching compounds, they are compatible with gypsum pours. A
Portland-based patching compound will cause a chemical reaction that could lead
to bonding issues.
We all
have a responsibility to provide the end user with quality products and
installation. As the saying goes, it starts from the GROUND UP!!