It’s easy to say, “We always
install according to Carpet & Rug Institute CRI-104 Commercial Installation
Standards.” The reality is that it is very tough to do when the amount and type
of floor prep is extensive and the owner doesn’t want to pay for what needs to
be done.
One flooring contractor
bid the job “per plans and specs” and included a small amount for “minor floor
prep.” When they were finally able to
get on the job site, it was discovered that asbestos abatement had been done,
including the removal of existing asbestos tile and old cut-back adhesive. A shot-blasting machine was used to remove
adhesive residue; while the adhesive was removed, so was the smooth surface of
the concrete leaving a very rough, powdering surface. In addition, there were depressions or
stripes left in the floor where the shot-blast equipment overlapped. Many floor areas had cracks and small holes.
Seeing a problem, the
alert project manager for the flooring contractor had an IICRC/FCITS certified
flooring inspector walk the job and provide a report. The inspector’s report said that the floor
was unsuitable in its present state to receive carpet (or any floor covering),
referring to CRI 104 Commercial Installation Standard, 6.1 and 6.2 which said
that “cracks over 1/8”. ..depressions over 1/32”..must be patched…powdering
surfaces must be sealed.” The project
manager also has the manufacturer of the carpet send in a representative to
inspect the substrate. The mill’s report
confirmed that the floor must be patched (as a minimum) and sealed or
completely resurfaced.
A self-leveling
polymer-type cementitious underlayment was not acceptable to the client because
of cost. After carefully looking at all floor
space, the project manager determined that 100% of the common and perimeter
areas must be skim-coated, and at least 50% of the interior office space, and
100% of the floor must be sealed to address the powdering condition. A change order was presented for approval based
on expected cost plus overhead and profit. The basis for the change order was
that the flooring contractor had not had an opportunity to evaluate actual site
conditions prior to accepting a contract; that the general contractor and the
client had not disclosed potential substrate problems; that actual floor
conditions were not typical of such a job; that the specified products and type
of installation could not be furnished without potential failure.
To the project manager’s
surprise, the client responded that “our project engineer has determined only
‘minor’ floor prep is needed and this should be covered under the scope of the
original bid document’s plans and specs which called for installation according
to CRI 104 Standards.” The project
manager was adamant that this was not a case of minor floor prep where one is
patching a few pock marks, holes, or cracks, and pointed out that the entire
finished surface of the concrete had been removed during shot-blasting, leaving
a powdering surface; that shot-blasting left depressions of varying depths
(over-lap marks) which are readily visible; that the action of shot-blasting
contributed to pock marking, holes, and other surface imperfections, all of
which must be filled.
As he should have done,
the flooring contractor refused to proceed with the work until he was either
given a suitable surface upon which to install the specified materials OR was
paid to provide a suitable surface. While
there was a stalemate for several days, the client finally approved the change
order. The patching was done, the job
installed, and the flooring contractor got paid.
Almost any job should have some floor prep and
patching. While it is easy to quote CRI
104 and 105 standards, it can be very tough to turn a standard into reality
when owners and general contractors don’t want to pay for the work. It is crucial that your proposals clearly
define the scope of work on floor prep. Otherwise, you may be forced to do the job
without any extra money or come back and redo the job after it fails.
This website stores data such as cookies to enable important site functionality including analytics, targeting, and personalization. View our privacy policy.
Report Abusive Comment